Good day,
Q: was there a set-back in development -
Nov 17 (Reuters) - Nvidia's (NVDA.O), opens new tab new Blackwell AI chips, which have already faced delays, have encountered problems with accompanying servers that overheat, causing some customers to worry they will not have enough time to get new data centers up and running, the Information reported on Sunday.
The Blackwell graphics processing units overheat when connected together in server racks designed to hold up to 72 chips, the report said, citing sources familiar with the issue.
Why do you think you're right?
Good day.
Even though there have been several attempts to resolve the issue this will not happen during the time frame of the question. This is a time frame update forecast.
Why might you be wrong?
Bad data from open source.